2025 Austin Arena Construction and Drainage Project update

Tuesday, December 2, 2025

  • 2025: Austin Arena Construction and Drainage Project update
The renovations to the north end of the Austin Arena are nearly complete. The 2025 Town budget projected $1.7 million in expenses for the project design and construction.  
The project was funded by using the following:
Source
Amount
 
ARPA Federal funding (COVID relief)
$400,000.00
Fennell Street parcel sale proceeds
$415,000.00
Unappropriated funds from prior years
$785,000.00
2025 Parks building appropriation
$100,000.00
 
 
Total
$1,700,000.00
 
Project expenses paid in 2025 as of 12/01/2025:
Vendor
Description
Amount paid to date
King & King
Architect
$28,862.00
A-Verdi
Equipment storage
$2,560.00
Bellows Construction
General contractor
$760,360.72
Kuehne Construction
HVAC contractor
$28,975.00
O’Connell Electric
Electrical contractor
$93,636.75
 
 
 
Total
 
$914,394.47
 
A final project report will be posted when payment of all project expenses are completed.