2025 Austin Arena Construction and Drainage Project update
Tuesday, December 2, 2025
-
2025: Austin Arena Construction and Drainage Project update
The renovations to the north end of the Austin Arena are nearly complete. The 2025 Town budget projected $1.7 million in expenses for the project design and construction.
The project was funded by using the following:
Source
|
Amount
|
ARPA Federal funding (COVID relief)
|
$400,000.00
|
Fennell Street parcel sale proceeds
|
$415,000.00
|
Unappropriated funds from prior years
|
$785,000.00
|
2025 Parks building appropriation
|
$100,000.00
|
|
|
Total
|
$1,700,000.00
|
Project expenses paid in 2025 as of 12/01/2025:
Vendor
|
Description
|
Amount paid to date
|
King & King
|
Architect
|
$28,862.00
|
A-Verdi
|
Equipment storage
|
$2,560.00
|
Bellows Construction
|
General contractor
|
$760,360.72
|
Kuehne Construction
|
HVAC contractor
|
$28,975.00
|
O’Connell Electric
|
Electrical contractor
|
$93,636.75
|
|
|
|
Total
|
|
$914,394.47
|
A final project report will be posted when payment of all project expenses are completed.